|
| R E S T O R A T I O N A N N O T A T I O N S |
|
| |
Special Benefit
Saturday, July 17, 2010
Reception at the Liberty Theatre
McTavish Room, 324 12th Street.
Enter through the Astor Building 12th Street entrance (door north of Jonathon's), use the elevator or
more...
|
| |
The Hydraulic Riveter
Saturday, April 3, 2010
Since we got the firebox
into the boiler, we have also spent a lot of time building a hydraulic riveter - a big clamp to squeeze the rivets in place as they will be too long
more...
|
| |
Preparing to rivet the mudring
Saturday, March 27, 2010
Since we got the firebox
into the boiler, we have been preparing it for riveting. We have had to build some tools, including the cutter for the countersink, and an "old
more...
|
| |
Preparing to rivet the mudring
Saturday, March 27, 2010
Since we got the firebox
into the boiler, we have been preparing it for riveting. We have had to build some tools, including the cutter for the countersink, and an "old
more...
|
| |
Preparing to rivet the mudring
Saturday, March 27, 2010
Since we got the firebox
into the boiler, we have been preparing it for riveting. We have had to build some tools, including the cutter for the countersink, and an "old
more...
|
| |
Preparing to rivet the mudring
Saturday, March 27, 2010
Since we got the firebox
into the boiler, we have been preparing it for riveting. We have had to build some tools, including the cutter for the countersink, and an "old
more...
|
| |
Firebox is inside the Boiler
Saturday, January 16, 2010
The weekend of January 9-10,
2010 marked another major step in the restoration of SMV 21. The entire boiler was raised up on cribbing so that the new firebox could be rolled
more...
|
| |
The Firebox goes in (photo sequence)
Saturday, January 9, 2010
In order to get the
firebox into place we raised the entire boiler on cribbing. We lifted the smokebox and each back corner a few inches at a time using our overhead
more...
|
| |
The Firebox goes in (photo sequence)
Saturday, January 9, 2010
In order to get the
firebox into place we raised the entire boiler on cribbing. We lifted the smokebox and each back corner a few inches at a time using the overhead
more...
|
| |
The Firebox goes in (photo sequence)
Saturday, January 9, 2010
In order to get the
firebox into place we raised the entire boiler on cribbing. We lifted the smokebox and each back corner a few inches at a time using our overhead
more...
|
| |
The Firebox goes in (photo sequence)
Saturday, January 9, 2010
The firebox was ready and
waiting with the mudring pinned in place on it. Next step was to lower it down onto four pieces of pipe so it can be rolled into
more...
|
| |
The Firebox goes in (photo sequence)
Saturday, January 9, 2010
As we raised the firebox
we had to ease the mudring into the boiler - a very tight fit. We were able to get it started in on most of the way around and at the end of the day
more...
|
| |
New equilizer beam machined
Friday, December 18, 2009
One of the four equilizer
bars for #21 was missing so we have been machining a new one. This has been a fill-in project on the large horizontal milling machine in the shop.
more...
|
| |
Working on the new equilizer beam
Friday, December 18, 2009
One of the four equilizer
bars for #21 was missing so we have been machining a new one. This has been a fill-in project on the large horizontal milling machine in the shop.
more...
|
| |
FRA inspector visits the shop
Monday, December 7, 2009
On December 7th we were
visited by Gary Groff and his assistant Howard Gehrke. Mr. Groff is the Steam Locomotive Inspector for the Federal Railroad Administration Region 8.
more...
|
| |
Rebuilding the Lead Truck
Saturday, September 5, 2009
Rebuilding #21's lead truck has
been one of our recent projects. It had been extensively modified and in a pretty haphazard way. The upright pedestals are not original and came off
more...
|
| |
Rebuilding the Lead Truck
Saturday, September 5, 2009
Here we have temporarily placed
the "Rolling Swing Arms" and the square stock "rails" on the front of the lead truck for visualization purposes. There was
more...
|
| |
Rebuilding the Lead Truck
Saturday, September 5, 2009
Here is a close-up of
#21's blueprint showing the front truck as originally planned. The two 9" long heart shaped arms hanging down are the "rockers".
more...
|
| |
Rebuilding the Lead Truck
Saturday, September 5, 2009
This closeup photo shows the
fireman's side of the lead truck with the journal box (black casting) sitting on the brass which contains babbit material that rides on the
more...
|
| |
Oil Tank Painted
Wednesday, July 15, 2009
Here is the oil tank
inside Lektro's state of the art paint booth with a shiny new coat of black Imron paint. It has since been moved back to our shop where over the
more...
|
| |
Actually it was badly orangepeeled!
Saturday, August 23, 2008
And if the orangepeel wasn't
enough, the paint wasn't completely cured despite the heat that was applied in the spray booth. So we carefully sanded as best we could. We
more...
|
| |
Restored Tender Frame goes on its Trucks
Tuesday, August 19, 2008
A red letter day for
the tender restoration. Dan Hess hauled the restored and freshly painted tender frame from the POA boatyard to the tracks adjacent to the Red Lion.
more...
|
| |
Tender frame at Red Lion
Tuesday, August 19, 2008
A red letter day for
the tender restoration. The restored and freshly painted tender frame was lifted onto its trucks - back on the rails.
more...
|
| |
Tender frame up and over
Tuesday, August 19, 2008
A red letter day for
the tender restoration. The restored and freshly painted tender frame was lifted onto its trucks - back on the rails.
more...
|
| |
Tender frame eased onto trucks
Tuesday, August 19, 2008
A red letter day for
the tender restoration. The restored and freshly painted tender frame was lifted onto its trucks - back on the rails.
more...
|
| |
Casey is oh-so-tired.
Tuesday, August 19, 2008
The restored and freshly
painted tender frame is back on the rails and near the restoration shop where it will receive a new timber deck. After the water tank is painted it
more...
|
| |
Paint touch up for tender truck
Sunday, August 10, 2008
Both tender trucks have now
been assembled and we are getting ready to move them to the track where they will meet up again with the frame. While we had nice weather John took
more...
|
| |
Half round added to combing edge
Sunday, July 27, 2008
All of the tank structure
is complete so it is time for the decorative touches.
This half round is shaped to fit the combing edge and will be riveted in place.
Sealant has
more...
|
| |
Forge Anyone?
Saturday, July 26, 2008
This little gem got a
lot of use as each and every one of the hundreds of rivets in the tender was heated within its brick lined walls.
more...
|
| |
Oil Tank Repairs
Sunday, July 6, 2008
A number of rivets in
the oil tank were badly corroded and needed to be replaced. Here Casey is grinding off the heads of those rivets before punching them out so that
more...
|
|
| |
Ready and Waiting
Sunday, June 22, 2008
These are the wheels for
the leading and trailing trucks. They have been cleaned and painted and they await space and time in the shop where the trucks will be assembled.
more...
|
|
| |
Old Water Tank Rusted Through
Tuesday, May 31, 2005
Here is a good shot
of the engineers side of the SMV #21's tender water tank showing some of the holes that have rusted through. It is pretty obvious from this
more...
|
|
| |
Tender Sits in Storage
Monday, May 30, 2005
While we worked at restoring
#21, her tender waited patiently for her turn in the shop. Finally in 2005 we obtained an Oregon Heritage Foundation matching fund grant to restore
more...
|
|
| |
Crown Sheet Removal
Wednesday, December 4, 2002
Here is an rare view
of the top of the firebox crown sheet from inside the boiler, looking to the rear. We are in the process of flame cutting the radial crown staybolts
more...
|
|
| |
Machining the Throttle Body
Thursday, August 29, 2002
Here the throttle body is
"chucked up" in a vertical turret lathe to cut new seats. This is the position the throttle mounts in the dome and its easy to see how the
more...
|
|
| |
Machining the Throttle Spool
Thursday, August 29, 2002
The throttle spool is in
our tracer lathe, having just had the two seats cut. They are the shiny bands near the right and left ends. Both seats were cut at a 20-degree angle
more...
|
|
| |
Tapping Washout Plug Holes
Thursday, August 22, 2002
There are four washout holes,
located just above the mudring in the new section of the backhead (There are 15 or so of these holes throughout the entire boiler). Their purpose
more...
|
|
| |
Dry Pipe Cut
Thursday, August 8, 2002
#21 is fitted with a
Ruston Balanced Throttle which is located in the steam dome. This is the large dome in the middle which is easily seen in all the photos. It is
more...
|
|
| |
Firebox Door Sheet Flanged
Tuesday, July 16, 2002
The entire flanging process can
be seen in this photo. Notice how the new sheet is clamped to the old sheet/die near to the edges to be formed. Besides using ARPA’s one million BTU
more...
|
|
| |
Outer Wrapper Patches Welded
Friday, July 5, 2002
The sides of the boiler
wrapper down low and under the cab wasted away from outside. A new patch panel was cut bent and drilled. And is now being welded in place. The bolts
more...
|
|
| |
Firebox Door Sheet Die Corners Added
Saturday, June 29, 2002
The old riveted firebox has
seams where the sheets overlapped over each other. The door sheet was against the mudring extending about one inch past the seam, tapering down to
more...
|
|
| |
Firebox Door Sheet Formed
Tuesday, June 11, 2002
John Niemann heats the doorway
hole in the firebox door sheet before bringing the 600 ton press down to complete the forming of the
more...
|
|
| |
Come Ring the Bell
Sunday, May 19, 2002
#21 bell was stolen in
the early 1980’s while the locomotive was stored in Northern California. While ARPA is still looking for #21 original bell, the bell you see was
more...
|
|
| |
Mudring Rivet Removal
Tuesday, April 30, 2002
Having removed the firebox flue
sheet, we now have to remove the mudring. This means driving out a couple of hundred 7/8” diameter rivets about 6 inches long.
In the old
more...
|
|
| |
Mudring Rivets Get Drilled
Monday, April 29, 2002
Casey Cochran tries out ARPA’s
recently acquired magnetic base drill, which was purchased with funds from recent fund raisers. The mag drill weighs about 90 pounds so Dennis Guyon
more...
|
|
| |
Students from AHS help
Saturday, March 9, 2002
A group of students from
Astoria High School's "Club de Union Juvenil" helped to clean out the inside of SPS 273 shortly after it arrived in Astoria.
more...
|
|
| |
Backhead Doorway Flanged
Thursday, March 7, 2002
We have started to form
the new manhole doorway in the new backhead. The female die was bolted to the bottom of the new backhead plate. The die was then clamped to a platen.
more...
|
|
| |
Flanging the Backhead
Tuesday, June 5, 2001
Work on the back of
the boiler is progressing carefully and steadily. We have built a die to flange the compound radius bends in the backhead (outside, back of the
more...
|
|
 |
|